Size a Windows patch window before the maintenance night starts.

Model staged patch duration from endpoint count, batch size, safe concurrency, measured download, install, reboot and validation time, expected retries, and a safety reserve. Compare the estimate with the maintenance window you actually have.

Your figures stay in this browser. Nothing is uploaded or saved.

Deployment scope and staging

Use representative measurements from a pilot. Batch size is the administrative wave you approve; concurrency is how many endpoints can progress at the same time inside that batch.

Measured endpoint timing

Use the slower representative systems, not the fastest lab computer. Reboot time should include service recovery needed before validation.

Modeled maintenance window

Results update immediately. Sequential batches are assumed; endpoints within each concurrency wave run in parallel.

Administrative batches—
Concurrency waves—
Base deployment time—
Retry allowance—
Total modeled duration—
Window fit—
Remaining / overrun—
Modeled max endpoints—

Published formulas

Batches = ceiling(endpoints ÷ endpoints per batch)

Concurrency waves = sum of ceiling(endpoints in each batch ÷ concurrent endpoints)

Base duration = concurrency waves × (download + install + reboot + validation minutes)

Retry duration = ceiling(expected retry endpoints ÷ concurrency) × (retry + validation minutes)

Total duration = base duration + retry duration + safety reserve